Hi,
We have materials using group strategy 40 or 63 in Planning tab MRP2
view,
the consumption mode = 2 Backward/forward consumption
with also a consumption horizon for bwd and fwd.
we create PIR like by example
PIR periode 1 10000
PIR periode 2 5000
both periods are in the past let's say.
when we create a sales order, automatically the standard reduce periode 2 before periode 1.
is there a possibility to do the same kind of PIR consumption from the oldest to the recent ones in case we use strategy 40 or 63.
That means in our example, the sales order reduces first period 1 and next period 2
for the strategy 10, the system behaviour is different because we found
OSS notes explaining that the oldest PIR (mean Periode 1) are consumed
first.
which it is not the case for our materials with strategy 40 or 63.
Another different logic in SD module if we create a scheduling agreementand we create slaes order in reference to this SA, the SA schedules
lines are consumed by sequence from the past to the future.
Thank for your help;