Hi PP Experts,
Our client have an issue with a Product
MRP type V1 (Manual Reorder Point with External req,)
ROP-1500
Lot Size PK, Planning calendar W01 ( Period begins on Monday)
Minimum Lot size - 2000
The MRP views of material are attached along with for more details.
Consumption to Production Order made using CO27.
MRP Run is done in Background NETCH running every night at 00:15 and NEUPL running weekly on Saturdays.
As per consumption (from MB51), on 11.1.2016 the stock fell below ROP 1500.
Till today, PR is not generated. I would expect the MRP run on 12.1.2016 should trigger the PR generation.
Planning file entry is also not created for the same.
What could be the possible reasons for non generation of PR? And what changes in the master needs to be done to generate the Purchase Requisition through MRP.
Thanks & Regards,
Satchidanand