Purchase Requisition not generated by Background MRP job.

$
0
0

Hi PP Experts,

 

Our client have an issue with a Product

 

MRP type V1 (Manual Reorder Point with External req,)

 

ROP-1500

 

Lot Size PK, Planning calendar W01 ( Period begins on Monday)

 

Minimum Lot size - 2000

 

The MRP views of material are attached along with for more details.

MRP1.png

plng cycle.png

mrp2.png

plng calendar.png

mrp 3.png

 

availab chk.png

require list.png

Consumption to Production Order made using CO27.

 

MRP Run is done in Background NETCH running every night at 00:15 and NEUPL running weekly on Saturdays.

 

As per consumption (from MB51), on 11.1.2016 the stock fell below ROP 1500.

requirement list.png

 

Till today, PR is not generated. I would expect the MRP run on 12.1.2016 should trigger the PR generation.

 

Planning file entry is also not created for the same.

 

What could be the possible reasons for non generation of PR? And what changes in the master needs to be done to generate the Purchase Requisition through MRP.

 