Hi experts,
In SAP APO PPDS we have the production plan previously set by the company, daily I execute the Heuristic SAP_PP_002 in order to attend new sales orders when the process orders are not sufficient to meet them, in this case the system must generate planned orders.
We have the following case in which we do not receive new sales orders and the system creates new planned orders:
START AVAILABLE TYPE QUANTITY AVAILABLE
DATE DATE DOCUMENT
29.MAR.2016 01.APR.2016 ProcOrd (L) 1,000 1,000
01.APR.2016 Sales Order 900 100
07.APR.2016 Sales Order 200 -100
05.APR.2016 08.APR.2016 ProcOrd (L) 1,000 900
13.APR.2016 15.APR.2016 ProcOrd (L) 1,000 1,900
20.APR.2016 22.APR.2016 ProcOrd (L) 1,000 2,900
27.APR.2016 29.APR.2016 ProcOrd (L) 1,000 3,900
If we execute the heuristic SAP_PP_002 the system generates the following planned order:
07.APR.2016 07.APR.2016 PlanOrd 100 0
We can care the sales order of 200 units for 07.APR.2016with the process order that starts 05/APR/2016
We can not change the date and amount of process orders because it is a plan previously established by the company, only we can create new planned orders
What I can do to make the system does not generate the planned order of 07.APR.2016?
Maybe we have to execute other heuristic, what heuristic we have to execute?
Regards,
Arnulfo Cordero Pradel