Hi people , i`m trying to configurate release strategies for purchase requisition where the main characteristic is de WBS Element which has been selectec for each item of the document. The relase procedure is at item level , not header.
PSP_PNR Work breakdown structure element (WBS element) ( CHAR 24 )
So i picked that field and added it to my release Class .
What i need to do know is to create the strategies only considering part of the WBS Element Code , for example , if i have all these WBS Elements defined :
PN-EMS-0653
PN-EMS-0654
PN-EMS-0655
PP-EMS-0123
PP-EMS-0124
PP-EMS-0125
I would need to create 2 release strategies , one for the WBS Elments that start with "PN-EMS" and one for the WBS Elements that start with "PP-EMS" .
I did the test and when i´m doing the clasificacion on each release strategy i would set the values :
Strategy #1
CHAR_WBS : PN-EMS*
Strategy #2
CHAR_WBS : PP-EMS*
Where CHAR_WBS is the characteristic that i created which i linked to the CEBAN-PSP_PNR field.
I also checked the "Unformatted Entry" check box under the "Addnl Data" tab for the characteristic but it`s still not working. The strategy wont activate. Does anybody have any clue on how i should populate the value of the characteristic for it to consider all the values related to the WBS Elements that start with Partial WBS Elemnt Name.
Thanks a lot for any tip !