Hi All,

 

I have the following case:

 

I got a Production Order in "closed" status.

 

So the user make a mistake and they need to reverse all the production order.

 

I know that run a Disassembly Order I can reverse the mistake but in the process I don't see how to reverse the Resources.

 

I'm doing the following steps:

 

1. Create a Disassembly Order and release it.

2. Create an Issue for Production for the Finished Goods.

3. Create an Receipt for Production to return the Raw Material.

 

I want to know what is the best way to reverse the resources. I don't want to use a journal entry.

 

Thanks in advance.

 

Regards