SAP ERP Community,
I'm trying to set a quantity threshold where the manufacturing plant will either be prompted to purchase the material externally, or manufacture internally.
For example, if the quantity required is lower than 100 pieces, I want MRP to generate a PldOrd with a BOM and Routing, etc.
However, if the quantity required is greater than 100 pieces, I want MRP to generate a PurReq to purchase based on source list/PIR etc.
Please advise of master data settings and transactions to execute this function, if possible.
-Matt