Hi PM Guru,
There is a weird issue that the cost elment for external material PR in PM order is different from that in the Material profile defined in Default value profile for PM external operation data.
Pls see details: (sorry for not being looked good)
1. Setting for External Profile:
2. Setting for Material Profile
3. Profile assignment against PLant + Order type
4. In order, when requesting a direct purchased material, the cost element is not 415000 provided that there is not default value setup in Order.
Please kindly me help investigate into other possibilities.