Dear Seniors,
Our customer uses only MTS for production.
It all starts from PIR inserted in MD61.
Based on that we have planned orders which have committed component quantities in the ATP process, and PLO becomes firm.
IF the PIR quantities are decreasing, then in MD04 I will see that I have ATP stock excess instead of having 0.
Do you know if there is a report in which I can see this excess for all materials ?
It is very important because a lot of components are shared between finished products, and in case of forecast decrease they need to be used for other parts. Otherwise they will be commited for planned orders which are not urgent.
Many thanks,